Western Canada Marine Response Corp. launched the first of 40 vessels for the Trans Mountain expansion project on June 12 in Prince Rupert. (WCMRC photo)

B.C. spill response plans in limbo after Trans Mountain decision

Nearly $150 million in new bases, personnel and ships are on hold

Plans to build six new spill response bases along B.C.’s coast are up in the air after last week’s court decision to halt the Trans Mountain pipeline expansion.

The six locations were part of a $150-million funding injection for marine safety that also included about 120 new hires and 43 new vessels.

The money was to be collected by Western Canada Marine Response Corp. from an impending toll on the expanded pipeline.

The corporation is an industry-funded organization tasked with responding to and cleaning up spills along B.C.’s coast.

READ MORE: WCMRC grows its fleet and spill response on the North Coast

But all of those plans are on hold now, according to its communications director Michael Lowry.

“We started working with Trans Mountain about five years ago on proposed enhancements for spill response on the coast,” said Lowry.

“So these enhancements have always been tied to the pipeline” by the National Energy Board.

Last Thursday, the Federal Court of Appeal shot down Ottawa’s approval of the Trans Mountain pipeline expansion on the grounds of environmental risk and Indigenous consultation.

The decision found that the National Energy Board “unjustifiably defined the scope of the project under review not to include project-related tanker traffic.”

READ MORE: B.C. ‘very disappointed’ by court decision to not hear Trans Mountain appeal

This allowed the board to ignore any harm increased tanker traffic could cause to Southern resident killer whales along the B.C. coast.

The court’s ruling means that the National Energy Board will have to redo its review of the Trans Mountain pipeline and the feds will have to reengage with Indigenous groups.

Its decision effectively put the $150 million in spill response improvements on hold.

The proposed spill response enhancements, Lowery said, were meant to reduce response time from six hours to two hours for Vancouver Harbour and down from 18-72 hours to six hours for the rest of the coast.

“But based on the ruling last week, there’s some uncertainty on what the next steps are,” said Lowry.

“We’ve put a pause on the work on our bases.”

The six bases would have been built in Vancouver Harbour, near Annacis Island in the Fraser River, in Nanaimo, Port Alberni, the Saanich Peninsula and Beecher Bay near Sooke.

The problem, Lowry said, is that several 25-year leases have already been signed.

“We’ve got leases in place with Port Metro Vancouver, the Fraser River, Nanaimo Port Authority and the Port Alberni Port Authority,” said Lowry.

“The next step for us was to proceed to issuing construction tenders. That’s paused right now.”

Lowry said that currently, the corporation won’t try to make any changes to those leases.

Instead, they’ll wait and see what happens with the pipeline expansion.

Some work has already started on the shipbuilding side.

“We have vessels being built in Prince Rupert, we have some being built down in Washington and we have some being built overseas,” he said.

“We can’t stop that work.”

READ MORE: Trans Mountain’s first oil spill response ship ready

Some of the new 120 planned employees have already been hired, Lowry said, but noted that they’ll keep their jobs because of the corporations phased-in hiring process.

“We’re bringing employees on based on the arrival of vessels so that we always have crew to man the new vessels,” he said.

“It’s certainly a bit of a balancing act.”


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Unique treasures to be found at Chilliwack Christmas Craft Market

The 44th annual event is the Chilliwack Community Arts Council’s largest fundraiser

Chilliwack toy drive brings in gifts, money to Ann Davis Transition Society

People dropped by Superstore to donate toys and more for those in need this holiday season

Seven Days in Chilliwack

A list of community events happening in Chilliwack from Nov. 18 to 24

Chilliwack RCMP find chemicals and cannabis extract in illicit lab

Marijuana may be legal but altering it using chemicals violates the Cannabis Act

Chilliwack RCMP seek suspects in rash of poppy donation box thefts

Incidents at four different locations in Sardis in the days leading up to Remembrance Day

Saving salmon: B.C. business man believes hatcheries can help bring back the fish

Tony Allard worked with a central coast First Nation to enhance salmon stocks

High-end B.C. house prices dropping, but no relief at lower levels

But experts say home ownership remains out of reach for many for middle- and lower-income families

Worker killed in collision at B.C. coal mine

Vehicle collision occurred at approximately 10:45 a.m. this morning

UPDATE: Hells Angels on scene after body found in Maple Ridge

Body was discovered beneath the Golden Ears Bridge

Mountie left with ‘significant’ injuries after driver attempts to flee traffic stop

Richmond RCMP are looking for a dark coloured Mercedes Benz

B.C. asking for tips on ‘dirty money’ in horse racing, real estate, luxury cars

Action follows a Peter German report on money laundering in B.C. casinos

Canadian dead more than a week after plane crash in Guyana: Global Affairs

Global Affairs said it couldn’t provide further details on the identity of the Canadian citizen

Children between 6 and 9 eligible for $1,200 RESP grant from province

BC Ministry of Education is reminding residents to apply before the deadline

Victoria spent $30,000 to remove John A. Macdonald statue

Contentious decision sparked controversy, apology from mayor

Most Read