Energy Minister Bill Bennett

Energy Minister Bill Bennett

Site C dam construction to start next summer

Province to take less revenue from BC Hydro to minimize its debt, says $8 billion project is the cheapest available option to meet demand

The B.C. government has given the go-ahead for BC Hydro to start construction on a third dam on the Peace River, with a delay of six months to try to work out settlements with area aboriginal communities and landowners whose properties will be flooded or cut off.

Energy Minister Bill Bennett said Tuesday an update of the construction costs upheld the $7.9 billion estimate for the Site C dam that was developed in 2010, but the estimate has risen.

Delaying the project six months from its original start date adds inflation and interest costs, and calculating the effect of the provincial sales tax replacing the HST bringing the total to $8.34 billion, and the province is establishing a “project reserve” of $440 million to bring the total estimated cost to $8.77 billion.

The project reserve is in case of unforeseen events such as a rise interest rates during the eight-year construction period.

BC Hydro CEO Jessica McDonald said the six-month delay provides time to work out agreements with Treaty 8 First Nations who have declined settlement offers. The federal-provincial environmental review panel gave the go-ahead for the project in May, but noted its unavoidable impacts on aboriginal hunting, fishing and trapping rights that are assured by the 1899 treaty.

A group of Peace valley landowners has already started legal action against the project, having refused offers from BC Hydro to buy their land. Aboriginal groups in Alberta, downstream of the project, have also started court action against it.

NDP leader John Horgan called the decision “a $9 billion gamble” and repeated his call for a review by the B.C. Utilities Commission to see if the additional power is going to be needed by the time the dam is operating in 2025.

The BCUC will determine BC Hydro rates in the years ahead, and how much they will go up to pay for the most expensive public construction project in B.C. history. The government plans to mitigate BC Hydro rate impact by reducing the dividend the government takes from the power company’s operations each year.

Bennett said a review of alternative clean energy sources, including wind, solar and geothermal power, showed they can’t compete on price because they are intermittent sources that would require backup power.

 

Just Posted

Dancers from the Sts’ailes First Nation perform the eagle dance at a welcome banner dedication ceremony on Thursday, June 10. “Ey Swayel” is a Halq̓eméylem term translated as ‘a good day.’ (Adam Louis/Observer)
VIDEO: ‘A good day’ for Agassiz school as Sts’ailes welcome banner is dedicated

Banner hangs above the school’s entrance, welcoming students, staff and visitors

Kalyn Head, seen here on June 4, 2021, will be running 100 kilometres for her “birthday marathon” fundraiser on July 23. (Jenna Hauck/ Chilliwack Progress)
Chilliwack woman’s 100-km birthday marathon to benefit Special Olympics B.C.

Kalyn Head hopes run raises awareness, advocates for inclusion of people with intellectual disabilities

RCMP investigating June 15, 2021 crash. (Black Press file)
Chilliwack RCMP say crash into median led to impaired driver investigation

Chrysler 300 driver allegedly collided with tree on Spadina median in June 15 incident

UFV athletes were honoured for their strength and perseverance during the pandemic. (UFV photo)
Fraser Valley athletes recognized in year without sports

UFV Cascades athletes honoured for strength shown during the pandemic

Abbotsford council has given permission for Chilliwack to use the JAMES wastewater treatment plant for the disposal of trucked liquid waste until the end of September.
Chilliwack gets exemption to Abbotsford bylaw prohibiting liquid waste from other cities

Process in place until September while new facility under construction in Chilliwack

A small pod of Pacific white-sided dolphins pass by close to shore in Campbell River June 16, 2021. Still capture from video courtesy of Kimberly Hart
VIDEO: Dolphin sunset captured from Vancouver Island shore

Spectacular setting for view of travelling pod of Pacific white-sided dolphins

Police are asking for public assistance in locating Anthony Graham who has been charged with the murders of Kamloops brothers Carlo and Erick Fryer. (RCMP photo)
2 charged, suspect at large in killings of B.C. brothers linked to gang activity: RCMP

Kamloops brothers Erick and Carlo Fryer were found deceased in May on a remote Okanagan road

Albert Health Minister Tyler Shandro and Alberta Premier Jason Kenney unveil an opening sign after speaking about the Open for Summer Plan and next steps in the COVID-19 vaccine rollout, in Edmonton, Friday, June 18, 2021. THE CANADIAN PRESS/Jason Franson
Alberta 1st province in Canada to lift all COVID-19 public health restrictions

70.2% of eligible citizens 12 and older in the province have received a dose of the vaccine

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Fraser Health registered nurse Ramn Manan draws a dose of the Pfizer COVID-19 vaccine into a syringe at a walk-up vaccination clinic at Bear Creek Park, in Surrey, B.C., on Monday, May 17, 2021. THE CANADIAN PRESS/Darryl Dyck
‘Honour our fathers’ with COVID-19 vaccine protection, B.C. urges

109 new cases Friday, 75 per cent of 12 and up immunized

Canadian Prime Minister Justin Trudeau is seen during a joint news conference following the EU-Canada Summit, in Brussels, Belgium, Tuesday June 15, 2021. Trudeau says Canada is on track now to have 68 million doses delivered by the end of July, which is more than enough to fully vaccinate all 33.2 million Canadians over the age of 12. THE CANADIAN PRESS/Adrian Wyld
Vaccine deliveries enough to fully vaccinate all eligible Canadians by end of July

Three in four eligible Canadians now have their first dose, nearly one in five fully vaccinated.

A search is underway for a 75-year-old fisherman who went missing near Port Angeles Thursday evening. (Courtesy of U.S. Coast Guard)
Search continues for angler missing between Port Angeles and Victoria

Canadian, U.S. Coast Guard searching for 75-year-old man reported missing Thursday evening

Chief Public Health Officer Theresa Tam listens to a question during a news conference, in Ottawa, Tuesday, Jan. 12, 2021. The number of confirmed COVID-19 cases attributed to the highly contagious Delta variant grew in Canada this week. THE CANADIAN PRESS/Adrian Wyld
Canada’s public health agency reports spike in confirmed cases of Delta variant

More than 2,000 cases of the variant confirmed across all 10 provinces and in one territory

Most Read