Kinder Morgan appeals to energy board over permit delays for pipeline expansion

Company has failed to get a permit from Burnaby for TransMountain

Kinder Morgan Canada Ltd. (TSX:KML) wants the National Energy Board to clear the way for work on the Burnaby portion of its Trans Mountain pipeline expansion project.

A statement released by the company says it wants a determination from the board allowing the work to begin, even though it has failed to obtain municipal permits from the City of Burnaby.

Kinder Morgan says Burnaby’s “failure to act in a timely manner raises serious issues of jurisdiction” related to the $7.4-billion pipeline expansion from the Edmonton-area to a tank farm and port in Burnaby.

READ: Pipeline route through Chilliwack final, says Kinder Morgan

The company also wants the board to set up a process to make an ”expedited determination” about similar complaints in future.

Kinder Morgan already has energy board and federal approvals to twin the pipeline, more than tripling its capacity, but earlier this month CEO Steve Kean said delays in permits and regulatory approvals mean the project could be almost nine months behind schedule.

The pipeline is slated for completion by December 2019, but Kean said recent delays had pushed back about $340 million of project spending scheduled for 2017.

Burnaby Mayor Derek Corrigan says the president of Kinder Morgan Canada, Ian Anderson, complained of “inordinate delays,” when the two met earlier this week.

“He was in to put some pressure on me about how quickly the regulatory process was going with the City of Burnaby,” Corrigan says.

READ: Kinder Morgan commits up to $3 million for salmon protection

The mayor says he told Anderson he could not interfere with the process, either by telling city staff to hinder the pipeline approval or by clearing the way for it.

Kinder Morgan’s statement says while it awaits the energy board’s determination of its request, it remains willing to discuss solutions with the City of Burnaby.

But Corrigan says it’s not a matter of negotiation, it’s a matter of Burnaby completing its due diligence.

Part of the expansion project will upgrade a section of pipeline from Kinder Morgan’s Burnaby terminal to its Westridge marine terminal at the eastern end of Burrard Inlet and also expand the terminal to allow for a significant increase in oil tanker traffic. (The Canadian Press, CKNW)

The Canadian Press

Just Posted

Man who stole millions from Seabird Island band sentenced to 4.5 years jail

Stephen MacKinnon sentenced in Chilliwack court for stealing $2.3 million over eight years

Freezing temperatures expected in Lower Mainland

Snowfall warning ends, but surge or icy air to continue

Chilliwack Chiefs take gut punch from Merritt in 5-2 loss

Trying to hold off Langley and Surrey for the Mainland division’s second seed, Chilliwack faltered.

Chilliwack’s history celebrated during Heritage Week

Heritage Chilliwack partnering with Atchelitz and more for open house

Park and trails consultation sessions kick off on Feb. 24

City staff will be talking about some current parks projects like green gyms for example

VIDEO: Sphero programmable robot rolled out at Chilliwack Library

With kids already learning coding skills at school, local libraries offer access to fun practice

How to keep local news visible in your Facebook feed

Facebook has changed the news feed to emphasize personal connections. You might see less news.

B.C. man brings dog to court as ‘best witness’

Man is defending himself on charges of uttering threats, possessing weapon for dangerous purposes

Ball hockey fundraiser to honour Langley man lost to cancer

Annual tournament at UBC aims to raise $45,000 this year

Vancouver artist’s cartoon of Florida school shooting resonates

Cartoon shows football coach, one of the victims, meeting others killed in school shootings

Trudeau family arrives in India for state visit

Seven-day visit includes meeting with Indian Prime Minister Narendra Modi

Military seeks DNA experts to help ID missing war dead

Federal program recovers, identifies and arranges burials for Canada’s nearly 28,000 missing war dead

B.C. files new legal action against TransMountain pipeline

Province tries to uphold City of Burnaby bylaws, provoking Alberta

Most Read