Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

UPDATE: Chilliwack youth coach acquitted of sexual touching of a minor

BC Supreme Court justice finds reasonable doubt despite not believing the accused

Motorists were ‘driving like their own Indy 500’ before fatal Abbotsford crash, court hears

Family member declares defence request for 90-day jail sentence a ‘joke’

World champion SFU Pipe Band comes to Chilliwack

SFU Pipe Band will put on a celebration of culture, music and heritage at Chilliwack Cultural Centre

Seven Days in Chilliwack

A list of community events happening in Chilliwack from Feb. 24 to March 1

Chilliwack biologist to speak on climate change at Green Party AGM

Dr. Carin Bondar is an author, adjunct professor and an explorer who has discovered new species

VIDEO: Illicit drug overdoses killed 981 in B.C. in 2019, down 38%

Chief coroner says figures were down about a third in the province’s fourth year of the opioid crisis

UPDATE: Protesters dismantle blockade on Maple Ridge tracks

West Coast Express train service is expected to run again Tuesday morning

VIDEO: B.C.’s seventh coronavirus patient at home in Fraser Health region

Canada in ‘containment’ as COVID-19 spreads in other countries

B.C. takes over another Retirement Concepts senior care home

Summerland facility latest to have administrator appointed

Man pleads guilty to stabbing woman, off-duty cop outside North Delta elementary school

The suspect, whose name is under a publication ban, faced 10 charges in relation to this incident

RCMP pull office from Wet’suwet’en territory, but hereditary chiefs still want patrols to end

Chief says temporary closure of field office not enough as Coastal GasLink pipeline dispute drags on

Prescription opioids getting B.C. addicts off ‘poisoned’ street drugs

Minister Judy Darcy says Abbotsford pilot project working

Royals, Elvis, Captain Cook: Hundreds of wax figures find new life in B.C. man’s home

Former director of Victoria’s Royal London Wax Museum still hopes to revive wax figure tourism

Teck CEO says Frontier withdrawal a result of tensions over climate, reconciliation

Don Lindsay speaks at mining conference, a day after announcing suspension of oilsands project

Most Read