Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Chilliwack Chiefs clinch first place with win over Prince George

The Chiefs were out-shot 36-13 but goalie Daniel Chenard was superb in a battle of the BCHL’s best.

New Chilliwack YMCA was ‘worth the wait’ say visitors

Family Day will mark officially opening for new building, after sneak peek tours on Saturday

Nanaimo Clippers goalie steals a win from Chilliwack Chiefs

Landon Pavlisin was outstanding in the Clipper net, leading Nanaimo to a 2-1 road victory.

More people in Chiliwack coming in to shelters to get out of the cold

Ruth and Naomi’s went over-capacity this week to accommodate shelter guests coming in from the cold

Prominent Chilliwack realtor says he doesn’t know how child porn got on his computer

Closing arguments heard in Ian Robert Meissner’s trial for accessing and possessing child pornography

B.C. students win Great Waters Challenge video contest

Video, mural and song about saving the salmon claims the top prize

B.C. athlete takes home gold in freestyle aerials at Canada Games

Brayden Kuroda won the event with a combined score of 121.65.

Pedestrian in serious condition after hit by car downtown Abbotsford

A youth was also hit, suffered minor injuries, police say

Cabinet likely to extend deadline to reconsider Trans Mountain pipeline

New round of consultations with Indigenous communities is coming

B.C. government provides $75,000 towards salmon study

Study looks at abundance and health of Pacific salmon in Gulf of Alaska

Murdered and missing honoured at Stolen Sisters Memorial March in B.C.

‘We come together to make change within the systems in our society’

UBC researchers develop inexpensive tool to test drinking water

The tricoder can test for biological contamination in real-time

Most Read