Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Stephanie Higginson, president of the B.C. School Trustees Association, says people need to focus their attention on the upcoming byelection in Chilliwack. (BCSTA image)
‘Let’s not talk about Barry’ says BCSTA president on Chilliwack trustee

Higginson says impending Chilliwack byelection will require ‘laser focus’ to ensure balance of power

New Chilliwack Chief Ray Fust.
Chilliwack Chief Ray Fust in the mix for Swiss U20 roster spot

Fust is hoping to make the team that will compete in the World Junior Hockey Championships

An employee at a Chilliwack McDonald’s location tested positive for COVID on Nov. 21 (File photo by The Associated Press)
Employee tests positive for COVID-19 at McDonald’s restaurant in Chilliwack

One case was detected at the Vedder Road location, which briefly closed its doors

Asbestos bag from 2011. (Chilliwack Progress file)
New limits coming for asbestos at the Bailey Landfill in Chilliwack

Restricted to 20 bags per day per property because they don’t have capacity for larger loads

Cascade Falls Regional Park is one of several Fraser Valley parks that saw record usage during the summer of 2020. (File photo)
Residents flock to Fraser Valley parks amid pandemic

Some trails saw usage double during summer months of 2020

People wearing face masks to help curb the spread of COVID-19 cross a street in downtown Vancouver, on Sunday, November 22, 2020. The use of masks is mandatory in indoor public and retail spaces in the province. THE CANADIAN PRESS/Darryl Dyck
B.C. reports 17 COVID deaths, 1,933 new cases as hospitalizations surge over the weekend

There are 277 people in hospital, of whom 59 are in ICU or critical care

An aerial shot of Cedar Valley Lodge this past August, LNG Canada’s newest accommodation for workers at the project site in Kitimat. This is where several employees are isolating after a COVID-19 outbreak was declared last Thursday (Nov. 19). (Photo courtesy of LNG Canada)
Forty-one positive COVID-19 cases associated with the LNG Canada site outbreak in Kitimat

Thirty-four of the 41 cases remain active, according to Northern Health

Workers arrive at the Lynn Valley Care Centre seniors home, in North Vancouver, B.C., on Saturday, March 14, 2020. It was the site of Canada’s first COVID-19 outbreak in a long-term care facility. THE CANADIAN PRESS/Darryl Dyck
Rapid tests ‘not a panacea’ for care homes, Dr. Bonnie Henry says

B.C. lacks capacity for daily tests of thousands of workers

(Delta Police Department photo)
Cannabis edibles found in Halloween bag lead B.C. police to illegal lab

Delta police arrested a man and a woman while executing a warrant at a residential property Nov. 20

Join Black Press Media and Do Some Good
Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

A woman being arrested at a Kelowna Value Village after refusing to wear a mask on Nov. 22.(@Jules50278750/Twitter)
VIDEO: Woman arrested for refusing to wear mask at Kelowna Value Village

RCMP claims the woman was uncooperative with officers, striking them a number of times and screaming

B.C. Liberal MLA Shirley Bond questions NDP government ministers in the B.C. legislature, Feb. 19, 2020. (Hansard TV)
Cabinet veteran Shirley Bond chosen interim leader of B.C. Liberals

28-member opposition prepares for December legislature session

Motorists wait to enter a Fraser Health COVID-19 testing facility, in Surrey, B.C., on Monday, November 9, 2020. THE CANADIAN PRESS/Darryl Dyck
COVID-19: What do rising positivity rates mean for B.C.? It’s not entirely clear

Coronavirus cases are on the rise but the province has not unveiled clear thresholds for further measures

Most Read