Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Police tape is shown in Toronto Tuesday, May 2, 2017. Statistics Canada says the country's crime rate ticked up again in 2018, for a fourth year in a row, though it was still lower than it was a decade ago. THE CANADIAN PRESS/Graeme Roy
CRIME STOPPERS: ‘Most wanted’ for the week of May 9

Crime Stoppers’ weekly list based on information provided by police investigators

An injection kit is seen inside a Fraser Health supervised consumption site is pictured in Surrey, B.C., Tuesday, June 6, 2017. THE CANADIAN PRESS/Jonathan Hayward
Hope’s high rate of drug overdose noted in BC Coroners Service report

Up-to-date numbers not available yet for 2021, but Fraser Health deaths on the rise

A map showing where the most number of cases were recorded from April 23 to 29. This map, revealing a breakdown of infections by neighborhood, was pulled from a data package leaked to the Vancouver Sun last week (and independently verified).
36 Abbotsford schools flagged for COVID-19 exposures in the last 2 weeks, shattering record

Clearbrook Elementary recorded an ‘exposure’ on all 11 school days

Screenshot from security footage a young, thin cougar prowling on Oliver Crescent in Sardis on May 7, 2021. (Dustin Meyer photo)
VIDEO: Cougar sighting in residential Chilliwack neighbourhood prompts warning

Springtime cougar sightings likely due to cats following deer down to valley floor, says CO

<a href="Facebook users reported seeing a body on the side of the road this morning." target="_blank"></a>Facebook users reported seeing a body on the side of the road this morning. (File photo)
Man killed in fatal hit-and-run collision between Abbotsford and Chilliwack

Body reported at 6 a.m., police close North Parallel Road, single highway lane as they investigate

(The Canadian Press)
Trudeau won’t say whether Canada supports patent waiver for COVID-19 vaccines

‘Canada is at the table to help find a solution’

After Bobby Henderson apologized online for his comments to a Toronto reporter, the Langley Rivermen announced that he was no longer team coach and general manager and in fact, had ‘parted ways’ with the franchise in March. (file/Twitter)
Former Langley Rivermen coach and GM apologizes for comments to Toronto reporter

Bobby Henderson blames stress due to the pandemic for his ‘disparaging’ remarks

The body of Brenda Ware, 35, was found along Highway 93 in Kootenay National Park on Thursday, May 6, 2021. (RCMP handout)
RCMP ask for tips after woman’s body found in Kootenay National Park

Brenda Ware was found along Highway 93 in the park, 54 kilometres north of the town of Radium

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

People pass the red hearts on the COVID-19 Memorial Wall mourning those who have died, opposite the Houses of Parliament on the Embankment in London, Wednesday, April 7, 2021. On May 3, the British government announced that only one person had died of COVID-19 in the previous 24 hours. THE CANADIAN PRESS/AP-Kirsty Wigglesworth
For a view of a COVID-19 future, Canadians should look across the pond

Britain, like Canada, is one of the only countries in the world to delay second doses for several months

Edmonton Oilers’ Connor McDavid (97) celebrates his 100th point this season with Leon Draisaitl (29) against the Vancouver Canucks during second period NHL action in Edmonton on Saturday, May 8, 2021.THE CANADIAN PRESS/Jason Franson
Edmonton superstar McDavid hits 100-point mark as Oilers edge Canucks 4-3

NHL scoring leader needs just 53 games to reach century mark

Nuns of Mother Teresa’s Missionaries of Charity, carry some of her relics during a vigil of prayer in preparation for the canonization of Mother Teresa in the St. John in Latheran Basilica at the Vatican, Friday, Sept. 2, 2016. In which city did she do much of her charitable work? (AP Photo/Gregorio Borgia)
QUIZ: How much do you know about these motherhood issues?

In honour of Mother’s Day, take this 10-question quiz

Twenty-nine staff members at Sunrise Poultry Processors Ltd. in Newton have tested positive for the virus, according to an information bulletin from Fraser Health Saturday (May 8). The health authority issued a 10-day closure order, effective May 7. (Image: Google Maps)
29 staff test positive for COVID-19 at Surrey poultry processing plant

Meantime, outbreak over at Surrey Memorial Hospital

Most Read